Project


Exit 54 Pacific Motorway – Abraham Road

Client:

Queensland Department of Transport and Main Roads

Location:

Coomera, Qld

Completion:

Project Overview


The Department of Transport and Main Roads identified that due to an increasing population of the Coomera area, the Motorway interchange at Exit 54 northbound had significant safety concerns for the public.  These included long traffic delays for motorists and traffic queues that extended onto the motorway off-ramp during peak periods.  The need for improvement became of high importance for the region.

A new link road was designed between the current Exit 54 Motorway northbound off-ramp and Abraham Rd, along with upgrades to the Abraham Rd intersection.  The upgrades would resolve flooding issues of Abraham Rd, and a new slip lane between Abraham Rd and Days Rd would service local schools.  Upgrading the public facilities were also identified, with a new bus stop and footpaths to be constructed as part of the improvement works.

Neumann Contractors Pty Ltd became involved in the project after the original principal contractor entered financial administration and liquidation.  Taking over the project in December 2009 for DTMR, the works quickly came back on track for the client, with progress meeting the original deadlines.


Image
Image

Scope & Solution


Scope of Works

The scope of work included:

  • Clearing and grubbing of 22,000m2 of grassland,
  • Translocation of frog habitat wetland,
  • Demolition of existing drainage structures,
  • Removal and disposal of 5,000m3 of unsuitable material,
  • Importation and placement of 12,000m3 of embankment material,
  • Construction of major drainage culverts and end structures,
  • Importation of 4,500m3 of pavement gravels,
  • Dense graded asphalt pavements, including deep lift and wearing courses,
  • Installation of guidance and information systems,
  • Installation of road lighting and traffic signal infrastructure,
  • Perimeter fencing,
  • Landscaping of verges, batters and wetland areas.

How We Delivered


Challenges

  • The relocation of frog habitat was a task that was previously unfamiliar to the on-site staff.  Through consultation with environmental experts, a process of slabbing the habitat and relocating.
  • The amount of unsuitable material that needed to be removed and replaced proved time-consuming to the program.  The additional plant was allocated to the task to prevent the works from delaying the completion date.
  • The construction of major drainage structures proved challenging through the wetter part of the year; however, the team overcame the issue of controlling stormwater by implementing diversion drains and a series of control pumps.
  • The upgrade works on Abraham Rd needed to be phased so that live traffic would not be impacted, particularly given that the area contained a high number of schools and workplaces.
  • The team carefully thought out traffic Guidance Schemes to ensure that the construction works would not impact the public while maintaining a workable area for the contractor.
  • The take over from a previous Principal Contractor introduced additional challenges; however, these were all easily resolved with the client on time.

Innovation

Different methods of overcoming wet and unsuitable areas were suggested by Neumann Contractors, with these options being implemented by DTMR. These included the use of geofabrics, geotextiles, and bridging rock in particularly bad areas.

Gallery


Image
Image
Image
Image
Image
Image
Image
Image
Image
Image

Looking Ahead


The improvements to traffic flows could be immediately seen once the new roads were opened, proving that the upgrade works were in desperate need for the local community.

Image

Let’s Discuss Your Next Project


VIEW OUR OTHER PROJECTS


Image

Wynnum Road Widening

Image

Wacol Driver Training Facility

Image

Sunshine Coast Motorway Link Road

Image

Southwest 1 and Berrinba Wetlands

Image

Mount Lindesay Highway

Image

Maroochy Boulevard Interchange

Image

Kingscoast Estate Project

Image

Kawana Waters

Image

Kalimna

Image

Hope Island Road Duplication

Image

Bribie Island Road Duplication

Image

Beenleigh Redland Bay Road Upgrade

Image

Chinderah Bypass Project

Image

Gold Coast Convention Centre

Image

Ernest Henry Mine Tailings Dredging

Image

Lake Illawarra Channel Entrance Dredging

Image

Cadia Gold Mine Tailings Dredging

Image

Moura Mine Tailings Dredging

Image

Penrith Lakes Tailings Dredging

Image

Port Botany Container Terminal

Image

Port Kembla Tug Berth Dredging

Image

Superior Coal Tailings Dredging

Image

Sydney Water Desalination Project

Image

GPC – Tug Berth & Channel Dredging

Image

Tallebudgera & Currumbin Creeks Dredging

Image

Townsville Marine Project

Image

Corridor Sands Resource Dredging

Image

Corrie Channel Dredging

Image

Cullen Bay – Bhagwan Marine

Image

Currumbin Creek Annual Dredging

Image

Liddell Power Station Fly Ash Dredging

Image

Hellyer Gold Dredge Hire

Image

High Quality Sands – Coffs Harbour

Image

Iluka Boat Harbour Dredging

Image

Cudgen Lakes Resource Dredging

Image

Liddell Bottom Ash Dredging

Image

Maroochy Dredging Beach Nourishment

Image

Maroochy Replenishment Dredging

Image

Monreagh Dam Tailings Dredging

Image

Ok Tedi Tailings Dredging

Image

Ramsgate Baths Beach Nourishment

Image

South Channel Dredging

Image

Tallebudgera Creek Dredging

Image

Swansea Channel Dredging

Image

South Wavebreak Island Channel Dredging

Image

Coomera River Dredging

Image

Caval Ridge Tailings Dredging

Image

Canaipa Passage Channel Dredging

Image

Canaipa Passage Dredging

Image

Cabbage Tree Point Dredging

Image

Bundaberg Port Dredging

Image

Bundaberg Burnett River Dredging

Image

Bulga Mine Dredge Trial

Image

Broadwater Parklands

Image

Bellinger River Resource Dredging

Image

TNRP – Wide Bay Burnett

Image

Kinross Business Park Stage 9