Project


Bundaberg Burnett River Dredging

Client:

Department of Transport and Main Roads

Location:

Burnett River (near Kirby’s Wall) Bundaberg

Completion:

Project Overview


Severe flooding impacted the Burnett River. As a result, the navigational channel required dredging to restore the depth of the river’s navigational channels adjacent to Kirby’s Wall. A total of 65,700 cubic metres of sand and gravel was removed from the channels and placed behind Kirby’s Wall.


Image
Image

Scope & Solution


Scope of Works

Severe flooding impacted the Burnett River. As a result, the navigational channel required dredging to restore the depth of the river’s navigational channels adjacent to Kirby’s Wall. A total of 65,700 cubic metres of sand and gravel was removed from the channels and placed behind Kirby’s Wall.

TMR nominated two specific dredge areas:

  • Dredge Area A, adjacent and upstream of Kirby’s Wall, required 36,000m3 of material to be removed, and
  • Dredge Area B, downstream of Kirby’s Wall with almost 30,000m3.

Dredging to a maximum depth of 2.3m below LAT was required in both channel areas.

The dredged material was required to be placed behind Kirby’s Wall to fill in the area between the river bank and the rock wall. The spreader barge spread the material evenly to a height below +0.3 LAT.

Equipment Used

  • Dredge & Booster – The 450mm cutter suction dredge the Nu Endeavour was used for this project. In addition, a booster pump and pontoon were connected directly to the rear of the dredge to extend its pumping capability to reach the required distances to the disposal area (up to 1,700m).
  • Spreader Barge – We undertook the replenishment works behind Kirby’s Wall with a spreader barge with a three-wire anchoring system. The three-wire system allowed the spreader barge to winch across the fill area while discharged material. In addition, to ensure anchor lines didn’t come into contact with the top of the wall and cause damage, floating pontoons were employed adjacent to Kirby’s Wall.
  • Support Vessels – Other supports vessels included: a Workboat, the MV Tramp; Fuel Barge; Anchor Barge and several smaller tender vessels.

How We Delivered


Dredging Works

Dredging commenced at the upstream end of the channel and progressed downstream. The team added the additional pipeline for works in Dredge Area B.

Neumann Dredging completed the project on a 24 hour, seven days per week basis.

Innovations

  • Use of spreader barge to place the dredged material behind Kirby’s Wall
  • Use of a barred Bucketwheel to exclude oversize material from the pumping system

Challenges

  • Spreading the dredged material evenly and with tolerances with the spreader barge behind Kirby’s Wall
  • Post-flood debris and obstructions in the dredge area
  • Dredging unpredictable material – coarse sand, gravel, cobbles and boulders.
  • Wear and tear on machinery and equipment.
  • Strict dredging and fill tolerances.
  • Interfacing dredging works with shipping, and other marine vessels traversed the work areas.
  • We had to maintaine access to the busy boat ramp adjacent to Kirby’s wall.

Gallery


Image
Image
Image
Image
Image
Image
Image

Looking Ahead


Dredging commenced at the upstream end of the channel and progressed downstream. The team added the additional pipeline for works in Dredge Area B.

Neumann Dredging completed the project on a 24 hour, seven days per week basis.

Image

Let’s Discuss Your Next Project


VIEW OUR OTHER PROJECTS


Image

Wynnum Road Widening

Image

Wacol Driver Training Facility

Image

Sunshine Coast Motorway Link Road

Image

Southwest 1 and Berrinba Wetlands

Image

Mount Lindesay Highway

Image

Maroochy Boulevard Interchange

Image

Kingscoast Estate Project

Image

Kawana Waters

Image

Kalimna

Image

Hope Island Road Duplication

Image

Exit 54 Pacific Motorway – Abraham Road

Image

Bribie Island Road Duplication

Image

Beenleigh Redland Bay Road Upgrade

Image

Chinderah Bypass Project

Image

Gold Coast Convention Centre

Image

Ernest Henry Mine Tailings Dredging

Image

Lake Illawarra Channel Entrance Dredging

Image

Cadia Gold Mine Tailings Dredging

Image

Moura Mine Tailings Dredging

Image

Penrith Lakes Tailings Dredging

Image

Port Botany Container Terminal

Image

Port Kembla Tug Berth Dredging

Image

Superior Coal Tailings Dredging

Image

Sydney Water Desalination Project

Image

GPC – Tug Berth & Channel Dredging

Image

Tallebudgera & Currumbin Creeks Dredging

Image

Townsville Marine Project

Image

Corridor Sands Resource Dredging

Image

Corrie Channel Dredging

Image

Cullen Bay – Bhagwan Marine

Image

Currumbin Creek Annual Dredging

Image

Liddell Power Station Fly Ash Dredging

Image

Hellyer Gold Dredge Hire

Image

High Quality Sands – Coffs Harbour

Image

Iluka Boat Harbour Dredging

Image

Cudgen Lakes Resource Dredging

Image

Liddell Bottom Ash Dredging

Image

Maroochy Dredging Beach Nourishment

Image

Maroochy Replenishment Dredging

Image

Monreagh Dam Tailings Dredging

Image

Ok Tedi Tailings Dredging

Image

Ramsgate Baths Beach Nourishment

Image

South Channel Dredging

Image

Tallebudgera Creek Dredging

Image

Swansea Channel Dredging

Image

South Wavebreak Island Channel Dredging

Image

Coomera River Dredging

Image

Caval Ridge Tailings Dredging

Image

Canaipa Passage Channel Dredging

Image

Canaipa Passage Dredging

Image

Cabbage Tree Point Dredging

Image

Bundaberg Port Dredging

Image

Bulga Mine Dredge Trial

Image

Broadwater Parklands

Image

Bellinger River Resource Dredging

Image

TNRP – Wide Bay Burnett

Image

Kinross Business Park Stage 9