Project


Kinross Business Park Stage 9

Client:

CABP Group Pty Ltd

Location:

Kinross Estate, Heatherbrae, New South Wales

Completion:

Project Overview


The Kinross Estate is an industrial park developed by the CABP Group Pty Ltd in Heatherbrae, NSW. To develop the site, the final levels need to be elevated to above the forecast flood levels. Previous stages were filled by conventional construction equipment with sand sourced from the other side of Masonite Road. This project aimed to use dredging techniques to transport the sand without the significant inconvenience to local road uses of construction traffic crossing the Road.


Image
Image

Scope & Solution


Scope of Works

Stage 9 of the Kinross Industrial Estate required the importation of 40,000m3 of sand from a stockpile located on the other side of a major Road. Neumann Contractors were challenged to develop a technique where the sand could transferred hydraulically through a pipeline and placed directly into the embankment.

We could not use conventional dredging equipment due to the sensitivity of the local groundwater aquifer. Neumann proposed to use captured bore water (extracted under license) to feed a dry feed bin that would blend the sand and water and then pump the slurry under the Road to the fill area.

Neumann designed and fabricated the dry feed bin and then designed and constructed a bore water holding pond at the stockpile site. We installed a pump in the holding dam that fed the dry feed bin with the bore water, and a slurry booster pump was connected to the outlet of the bin. Twin 315mm poly pipelines were installed from the booster pump, under the Road and to the fill area. The team used one pipeline to deliver the slurry to the fill area, and we used the second to return the slurry supernatant water back to the holding pond for reuse. The sand was loaded into the dry feed bin with wheel loaders working in conjunction with dual-screen hopper stockpilers.

How We Delivered


Innovations

  • Design and fabrication of the sand dry feed bin,
  • The extraction, storage, use and re-use of bore water to hydraulically transfer the sand.

Challenges

  • Minimising the loss of bore water at the fill area.
  • Water proofing the bore water containment pond.
  • Maintaining safe navigational access for all boating traffic in this very popular and busy recreational waterway.

Gallery


Image
Image
Image
Image

Looking Ahead


All works were performed on time and within budget. The CABP Group were very satisfied with the outcome of the project.

Image

Let’s Discuss Your Next Project


VIEW OUR OTHER PROJECTS


Image

Wynnum Road Widening

Image

Wacol Driver Training Facility

Image

Sunshine Coast Motorway Link Road

Image

Southwest 1 and Berrinba Wetlands

Image

Mount Lindesay Highway

Image

Maroochy Boulevard Interchange

Image

Kingscoast Estate Project

Image

Kawana Waters

Image

Kalimna

Image

Hope Island Road Duplication

Image

Exit 54 Pacific Motorway – Abraham Road

Image

Bribie Island Road Duplication

Image

Beenleigh Redland Bay Road Upgrade

Image

Chinderah Bypass Project

Image

Gold Coast Convention Centre

Image

Ernest Henry Mine Tailings Dredging

Image

Lake Illawarra Channel Entrance Dredging

Image

Cadia Gold Mine Tailings Dredging

Image

Moura Mine Tailings Dredging

Image

Penrith Lakes Tailings Dredging

Image

Port Botany Container Terminal

Image

Port Kembla Tug Berth Dredging

Image

Superior Coal Tailings Dredging

Image

Sydney Water Desalination Project

Image

GPC – Tug Berth & Channel Dredging

Image

Tallebudgera & Currumbin Creeks Dredging

Image

Townsville Marine Project

Image

Corridor Sands Resource Dredging

Image

Corrie Channel Dredging

Image

Cullen Bay – Bhagwan Marine

Image

Currumbin Creek Annual Dredging

Image

Liddell Power Station Fly Ash Dredging

Image

Hellyer Gold Dredge Hire

Image

High Quality Sands – Coffs Harbour

Image

Iluka Boat Harbour Dredging

Image

Cudgen Lakes Resource Dredging

Image

Liddell Bottom Ash Dredging

Image

Maroochy Dredging Beach Nourishment

Image

Maroochy Replenishment Dredging

Image

Monreagh Dam Tailings Dredging

Image

Ok Tedi Tailings Dredging

Image

Ramsgate Baths Beach Nourishment

Image

South Channel Dredging

Image

Tallebudgera Creek Dredging

Image

Swansea Channel Dredging

Image

South Wavebreak Island Channel Dredging

Image

Coomera River Dredging

Image

Caval Ridge Tailings Dredging

Image

Canaipa Passage Channel Dredging

Image

Canaipa Passage Dredging

Image

Cabbage Tree Point Dredging

Image

Bundaberg Port Dredging

Image

Bundaberg Burnett River Dredging

Image

Bulga Mine Dredge Trial

Image

Broadwater Parklands

Image

Bellinger River Resource Dredging

Image

TNRP – Wide Bay Burnett